HR 6633
Passed a chamber
Requires the Federal Energy Regulatory Commission to write rules that direct utilities to use top-performing power conductors, meaning the wires that carry electricity, on new and substantially upgraded high-voltage transmission lines, with several exemptions.
Official title: High-Capacity Grid Act
Timeline each lane is a chamber; dates pull from congress.gov actions
House
Introduced
11-DEC-2025
Referred
11-DEC-2025
Approved by committee
21-JUL-2026
Reported
14-SEP-2026
On the calendar
14-SEP-2026
Passed
15-SEP-2026
Senate
Received
16-SEP-2026
- Directs the Federal Energy Regulatory Commission to issue regulations within one year of enactment that create a best-available transmission conductor class, using a methodology developed with the Secretary of Energy.
- Covers new transmission facilities under Commission jurisdiction and major modifications, upgrades, replacements, or reconductoring of existing ones.
- Exempts projects for which a utility filed a required permit or procured conductors before enactment, emergency repairs after disasters or officially designated emergencies, uses that would harm safety or violate a reliability standard, and uses that would significantly raise the cost per kilowatt-hour without a material gain in capacity, efficiency, or mechanical performance.
- Lets the Commission periodically review and update the designation methodology and the list of designated conductors to reflect technology improvements.
Covers an older version. The newest CRS summary describes the bill as of "Introduced in House" (11-DEC-2025); the text has changed since (Engrossed in House, 15-SEP-2026).
CRS is the Library of Congress's nonpartisan research office. Read it on congress.gov- Energy and Commerce Committee (House)
- Energy Subcommittee
- Energy and Natural Resources Committee (Senate)
Energy
■ 4 R
4 Republicans